How far in advance should I book crane equipment for a modular project in the UAE?

Considerably earlier than on a traditional project, ideally at the design development stage, because module dimensions, weight, and lift plans need to be finalized before fabrication is locked in, and crane and transport equipment for modular installation is often booked months ahead of the actual installation window. Waiting until modules are fabricated to plan equipment risks discovering a mismatch that's expensive to correct at that stage. Sparkline Group recommends engaging our crane planning team as early as possible in a modular project's design process. This early involvement has repeatedly helped clients avoid costly late-stage equipment changes. Reach out during your design phase rather than waiting until construction is imminent.