How is a tower crane removed once construction is complete?

Tower crane dismantling reverses the erection sequence - the jib and counter-jib are removed first, then mast sections are taken down from the top using a mobile crane positioned at ground level, continuing until the base section and foundation are clear. This is a planned, certified operation requiring the same lifting engineering discipline as the original erection.